This project involved the creation of a holiday park extension. The key components included installing 55nr concrete raft foundations, along with all services and infrastructure including interface with Northern PowerGrid, Yorkshire Water and Northern Gas.

The works also included foul and rain water drainage and connections into the existing adopted system and the construction of all roads and paths including a concrete imprinted and coloured kerbing system. The later stages of the project then involved landscaping works such as the creation of a new pond in line with the ecology works scope for the project.

Unprecedented rainfall throughout the works programme created many challenges to the day to day running of the site and the works throughout the programme, however these were overcome and the scheduled works went ahead as planned.